| Sludge Blend Tank Replacement - Project Overview |
| Clark County Project |
Work Order #15280 |
| Project Schedule |
Construction completed in 2006 |
| Project Type |
Replacement Project |
| Project Location |
Existing treatment plant site at 15100 NW McCann Road |
| Project Location |
John M. Peterson, P.E., (360) 993-8819 |
| Construction Costs |
$909,000 |
Project Overview
|
The Sludge Blend Tank mixes the solid components before they are moved to the aerobic digesters. Mixing the components helps release the gases as well as blend the different solid elements evenly. The former Sludge Blend Tank was failing due to advanced corrosion. A new tank, pumping system and odor control system have been constructed.
|
| Click on the map below to see a larger map of the project site. |
 |